Building Project Update – April 23, 2022

  • Contractor reported that the delivery of the steel package has improved from June 30 to May 30, 2022.
  • Duke has come out and are prepared to install the New Transformer once the Contractor complete the site work in front of the school.  We anticipate this to be done within 15 to 20 days.
  • We have all the paper work we need to submit for the Encroachment Agreement and this will be submitted on next week 
  • We are still on target with our completion date.  

 

 